Green Line Extension Executive Change Control Board Meeting

Regular Meeting
August 14, 2026 | 11:00 a.m.
Location: Green Line Extension Project Office - 6465 Wayzata Blvd., St. Louis Park, MN 55426 (5th Floor)


Agenda

  1. Welcome                                                                                                                    Action Required
  2. Minutes from June 12, 2026                                                                                     Approval
  3. Resolution 26-ECCB-007                                                                                          Approval
    • Approval of the use of project contingency in the amount of $656,803.24 for the Part 2 Change Order 0171 to the Systems and Tunnel Facilities (STF) Contract with Aldridge Parsons, a Joint Venture (APJV) to furnish and install an intrusion detection system and cameras between Opus Station and Smetana Road.
  4. Report on Change Orders
  5. Adjourn