Metro Plant Steam System Improvements And Turbine Rehabilitation Project

Project 808927

Text Alert Icons Project Alert

Project Update - August 20, 2026 (PDF).  See previous Project Updates below.

To receive project updates via email or text, sign up using the E-newsletter/SMS subscription form on the right.
 

Project Description

This project rehabilitates the existing steam turbine generator and makes improvements to the steam system in the solids management building to increase availability and to extend service life. The project scope items are summarized below.
  • Installs new generator, controls, and steam turbine components (by Siemens Energy under a separate contract with the Council).
  • Modifies existing turbine steam piping.
  • Installs instrumentation to monitor turbine, boiler feedwater, and steam.
  • Installs additional boiler feedwater treatment.
  • Installs vibration reduction system on structure.
Overhead photo of five people standing around the existing G7 steam turbine Photo 1: Existing G7 Steam Turbine  
 

Project Schedule

Notice to proceed was issued on July 11, 2025. 

Anticipated completion: Spring 2027
 

Project Updates

Project Update - August 20, 2026 (PDF) 272 kB

Project Contacts

For information, please contact:

Aaron Kuznia
Principal Contract Administrator, Construction Services
Email: [email protected]
Phone: 651-602-8926

Josh Kirk
Senior Engineer, Plant Engineering
Email: [email protected]  
Phone: 651-602-1268
 
Capital Improvement Program
Contact us
Aaron Kuznia
Principal Contract Administrator, Construction Services
Email: [email protected]Phone: 651-602-8926

Josh Kirk
Senior Engineer, Plant Engineering
Email: [email protected]Phone: 651-602-1268