Fridley Area Lift Station

Project 809400

Text Alert Icons Project Alert

Project Update - August 12, 2026: Link added to MPCA's L32A EAW web page.  See previous Project Updates below.

To receive project updates via email or text, sign up using the E-newsletter/SMS subscription form on the right.

 

Project Description

Metropolitan Council Environmental Services (Met Council), operator of the metro-area wastewater collection and treatment system, plans to build a new lift station in Fridley.

The existing lift station in Brooklyn Park is over 50 years old and has reached the end of its useful life. It lacks adequate storage, leading to sewer backups and odors. This site will be used as an odor control facility and to access pipes that cross the river.

The new lift station will be located on the east side of the Mississippi River in Fridley. The new facility will preserve wastewater system assets, improve system reliability, and accommodate community growth.

Map of Fridley L32A project showing lift stations on either side of the Mississippi River - the existing one near the west bank, and the future one on the east bank, with pipes under the river shown between them.

Project activities between 2021 and 2025

  • Conducted site survey and collected data
  • Performed soil borings to learn about site geology and soil conditions
  • Finalized recommended construction methods
  • Communicated and coordinated with cities, counties, and federal agencies to include their requirements in the design
  • Project design is 90% complete and built a design model

What's happening in 2026?

We are in the final design phase. In the next few months, we will finish the project plan and specifications and apply for the permits we need from regulatory agencies. We will reach out to our neighbors before selecting a contractor to inform them about the project and gather any initial questions or concerns that they have. 

We plan to host a meeting later this year to update the community on the final design plans and the anticipated construction activities, schedule, and impacts.  We will update the Community Meeting section below when the meeting date is confirmed.

Environmental Assessment Worksheet (EAW)

Read and submit comments on the EAW at the Minnesota Pollution Control Agency's (MPCA's) L32A EAW web page.
 

Planning: 2019 to 2021
Design: 2022 to 2026 (We are here.)
Construction: 2027 to 2031

Project timeline showing planning from 2019 to 2021, design from 2022 to 2026 (with a star that says "we are here" toward the end of this section), and construction and restoration from 2027 to 2031.

The next community meeting is being planned for late 2026.  Sign up using the E-newsletter/SMS subscription form on the right to be notified when the meeting is scheduled.

The new lift station will pump wastewater from the local wastewater collection system into the Met Council regional sanitary sewer system. A series of regional sewers then conveys the wastewater to the Metropolitan Wastewater Treatment Plant in Saint Paul.

The lift station will include communications equipment to monitor pumping equipment, and backup power to maintain reliable, uninterrupted operation.
 



 

  • What will happen to the Brooklyn Park site?
    • The Brookyln Park lift station will be demolished and decommissioned after the Fridley lift station is in operation. The odor control building and additional structures that house the mechanical and electrical equipment will remain onsite, as pipes will still cross from Brooklyn Park to Fridley under the river.
  • Why won’t the new lift station be built at the existing site in Brooklyn Park?
    • The site does not have enough space to expand the existing lift station for future use without acquiring additional properties.
    • The new site accommodates a large area, which is necessary for the construction of the new, larger lift station.
    • The existing site in Brooklyn Park will continue to house an odor control building and additional structures that house the mechanical and electrical equipment, as pipes will still cross from Brooklyn Park to Fridley under the river.
  • Did Met Council purchase the Camp Lockeslea property from the Girl Scouts?
    • Yes, Met Council purchased the property at 6900 East River Road in Fridley when the opportunity arose in 2014.
  • Will Met Council need the entire property for their lift station and other facilities?
    • No. After construction is completed, a large portion of land on the north side of the parcel will not be needed for buildings or maintenance of our facilities.
    • Once construction is completed, we will partner with interested agencies to explore opportunities for the remaining usable area.
  • Why will the new lift station site take five years to complete?
    • This will be the largest lift station in the Met Council system. It will be 110 feet in diameter and 70 feet deep.
    • Due to the lift station’s proximity to the Mississippi River, the depth and size needed for the new lift station, it must be built using a special method.
    • This project includes multiple components – building a new lift station in Fridley, repairing the pipes crossing the river, and decommissioning the existing lift station at the Brooklyn Park site.

 

Project Updates

Project Update - February 23, 2026 (PDF) 599 kB

Project Update - November 8, 2023 (PDF) 287 kB

Project Staff

Jeny Baroda, Principal Engineer, Interceptor Engineering
Tim Wedin, Assistant Manager, Interceptor Engineering
 

Project Contacts

For information, please contact:

Email: info@fridleyarealiftstation.com
Phone: 763-520-8650

Sign up for E-newsletter/SMS at the top right of the page.