Blue Lake Wastewater Treatment Plant Improvements Project

Project 809700

Text Alert Icons Project Alert

Project Update - August 6, 2026: Schedule updated. See below for previous Project Updates.
 

About this Project

Metropolitan Council Environmental Services (Met Council) is responsible for protecting public health and the environment through efficient and cost-effective wastewater collection and treatment for the Twin Cities region. ES is preparing a Facility Plan for improvements to its Blue Lake Wastewater Treatment Plant in Shakopee.

The draft facility plan for the Blue Lake Wastewater Treatment Plant Improvements Project outlines plant upgrades needed to serve anticipated growth in the southwest metropolitan area through 2050 and meet new water quality standards for phosphorus. Improvements to the Blue Lake Plant will help ES maintain service reliability, preserve assets at the existing facility, improve efficiency and safety, protect the environment, and partner with customers.

Schedule

The draft Facility Plan was completed in early February 2021. The public was provided an opportunity to weigh in on the plan at an online public information meeting and public hearing and during the public comment period from February 8, 2021 to March 25, 2021. The Facility Plan was finalized in late spring of 2021.

Work is scheduled as follows:

  • Drum Replacement: This work is currently ongoing and expected to be complete in September 2026.
  • Digester Construction: The design is complete and the project will be advertised for bid in September 2026, and is expected to be complete in summer to fall of 2028.
  • Liquids Improvements: This work is currently in detailed design, with work expected to be complete in summer to fall of 2030.

Public Information Meeting and Public Hearing

The Met Council project team hosted an online public information meeting and public hearing March 15, 2021.
 

Project Materials

Project Updates

Online Public Hearing and Comment Period Notification - February 25, 2021 (PDF) 748 kB

Blue Lake Wastewater Treatment Plant Improvements Facility Plan (PDF) 7.4 MB

Project Staff

Project Manager: Jason Peterson, Project Manager, Plant Engineering
 

Project Contacts

Contact project staff with questions or concerns about this project.

Email: [email protected]
Phone: 651-602-1614